Sungai Buloh MRT
Project Mass Rapid Transit Lembah Kelang: Jajaran Sungai Buloh – Kajang Package VI: Construction and Completion of Viaduct Guideway and Other Associated Works From Sg. Buloh To Kota Damansara Station (Pier DDS16 & DDN16 and Pier SBS11 & SBN13).
SCOPE | DATE | CONTRACT SUM | CLIENT |
BORED PILES | May 14 – Aug 14 | RM 2.51 mil | Gabungan Strategik Sdn Bhd |